Chastain supplied Phase III construction engineering services for a new full access, four-ramp interchange on new alignments. The construction included ramp pavements, embankments, reconstruction of two bridges, new toll plazas, retaining walls and highway lighting.

The new $19.2 million construction included:

I-90 & IL 173 Interchange 4
  • New full access, four-ramp interchange on new alignment.
  • New ramp pavements, embankments, reconstruction of two bridges.
  • New toll plazas.
  • Retaining walls.
  • Highway lighting.
  • Prepared all documentation required by IDOT.
  • Provided Level I and II Bituminous Concrete material testing, asphalt plant inspection.